Why Long Thanh Airport’s Catering and Ground‑Handling Projects Are Delayed
Dự án phục vụ mặt đất và nhà hàng Long Thành chậm tiến độ vì sao?
Nguồn: Vnexpress
The Civil Aviation Authority of Vietnam (CAAV) has asked the Ministry of Construction to approve a revised timeline for Component 4 of Long Thanh Airport’s first phase. Understanding why the airport’s catering and ground‑handling works are delayed helps reveal real challenges in large‑scale projects.
Contracts amended in June required six projects to be completed by 31 August. So far only the No. 2 aviation catering facility and the No. 2 ground‑handling and vehicle‑maintenance centre have reached the equipment‑installation stage.
The remaining four projects – the No. 1 catering facility, the No. 1 ground‑handling centre, and aircraft‑maintenance facilities No. 1, 3 and 4 – have not finished basic construction. Their work is still at the early building phase.
The CAAV said the delays stem from massive workloads, shortages of labour and construction materials, and fluctuating fuel prices. In addition, the shipping of specialised imported equipment has taken longer than expected.
Unfinished common technical infrastructure at the airport has also blocked contractors from organising work sites, building access roads, and connecting utility networks. Without these shared facilities, progress on individual projects is severely hampered.
The authority has set 24 December as the final deadline for construction and equipment installation, and it warned that no further extensions will be granted before the airport opens. This deadline marks the last chance to finish the pending works.
Bạn đã đọc xong bài này
Từ trong bài này
8 từ gợi ý · 0 từ đã tra
Từ gợi ý
Từ bạn đã tra
Bạn chưa tra từ nào trong bài này.
Luyện tập bài này
Luyện tậpĐọc tiếp
Latest NewsThể thao · B1 · 1 phút đọcWhy Kozo Tashima Is Challenging FIFA’s Leadership
Vì sao Kozo Tashima thách thức quyền lực của FIFA
Latest NewsDu lịch · B1 · 2 phút đọcConnecting All 34 Provinces: Why Vietnam’s $6.2 Billion Expressway Plan Matters
Kết nối 34 tỉnh thành: Vì sao kế hoạch 6,2 tỷ USD xây cao tốc của Việt Nam quan trọng?
Latest NewsKinh doanh · B1 · 2 phút đọcWhy Vietnam’s Leader’s Japan Visit Matters for Both Economies and Cultures
Chuyến thăm Nhật Bản của Tổng Bí thư Tô Lâm và ý nghĩa với kinh tế, văn hóa hai nước