Logo
Home
language
Chính sách quyền riêng tư·Điều khoản dịch vụ
Trang chủTừ vựngĐọc & NgheIELTS

Luyện đọc

Why Long Thanh Airport’s Completion May Slip to 2027‑2028
Kinh doanh · B1 · 2 phút đọc

Why Long Thanh Airport’s Completion May Slip to 2027‑2028

Sân bay Long Thanh có thể chậm tiến độ đến 2027-2028

Nguồn: Vnexpress

At a meeting with Standing Deputy Prime Minister Pham Gia Tuc, ACV reported that the third component of Long Thanh International Airport is almost finished, yet the project cannot meet its 2026 deadline. Understanding the reasons helps us see real‑world construction challenges.

ACV said construction of the third component is 88.6 % complete and disbursements have reached 57 % of the contract value. These figures show the work is far advanced but still not fully finished.

The developer also warned it cannot finish the whole component by the contractual deadline this year. ACV expects the major contracts for the passenger terminal, the first cargo terminal, the parking garage and the airport management system to be completed by June 2027.

ACV identified several obstacles. Some materials and equipment differ from contract specifications in manufacturer, brand, type, source or origin, and they were ordered, supplied and installed before ACV approved any changes. In addition, certain facilities were built according to construction drawings that do not match the approved technical designs, and some were constructed before the drawings were approved.

ACV said these issues must be resolved before the works can be formally accepted and the airport licensed to operate. It has asked the government to have the Ministry of Construction review all schedules and consider extending the first‑phase deadline to 2027 or 2028.

The delay is caused mainly by mismatched materials, unapproved design changes and construction that proceeded without final drawings. Because of these problems, the deadline for the first phase may be pushed back to 2027‑2028.

Bạn đã đọc xong bài này

Từ trong bài này

8 từ gợi ý · 0 từ đã tra

Từ gợi ý

Từ bạn đã tra

Bạn chưa tra từ nào trong bài này.

Luyện tập bài này

Luyện tập

Đọc tiếp

  • Why Inflated Bids and Payment Defaults Keep Rising in Vietnam’s Land Auctions
    Latest NewsKinh doanh · B1 · 2 phút đọc

    Why Inflated Bids and Payment Defaults Keep Rising in Vietnam’s Land Auctions

    Đấu giá đất: Giá bị đẩy lên do đặt giá ảo và nợ tiền

  • Why Vietnamese Banks Can't Deliver Cheaper Investment Loans
    Latest NewsKinh doanh · B1 · 2 phút đọc

    Why Vietnamese Banks Can't Deliver Cheaper Investment Loans

    Vì sao ngân hàng Việt khó giảm lãi suất cho vay đầu tư

  • New Durian Protocol Could Speed Thai Exports and Boost Chinese Consumer Trust
    Latest NewsKinh doanh · B1 · 2 phút đọc

    New Durian Protocol Could Speed Thai Exports and Boost Chinese Consumer Trust

    Hiệp định mới về sầu riêng: Thúc đẩy xuất khẩu Thái, tăng niềm tin người tiêu dùng Trung Quốc

0:000:00